Pacific Gas and Electric did not extend a high-inventory OFO beyond Wednesday.

El Paso plans to shut in Line 1300 between Roswell and Caprock on Tuesday and Wednesday next week for pipeline and valve replacement on the San Juan Crossover. Physical capacity of 620 MMcf/d at Lincoln Station will be lowered to zero during that period, the pipeline said. See the bulletin board for customer information on dealing with the shutdown.

Gulf South has scheduled about 24 hours of planned pigging maintenance starting at 8 a.m. June 16 on its Index 430 segment (the 8-inch and 10-inch diameter lines between Longview and Waskom in East Texas). See the bulletin board for a list of locations that must shut in during the work. Southwestern Electric Power‘s Pirkey Power Plant will not be affected, Gulf South said.