Rockies Express said it lifted a force majeure Thursday for its booster facility at the Wamsutter Echo Springs interconnect in Sweetwater County, WY.

Citing unplanned pipeline inspection and repairs along its Southwest Mainline (SWML), ANR said Thursday it is restricting SWML-CFTP capacity to only firm primary transportation until further notice.

NOVA said it will proceed as planned for an April 26-30 maintenance outage of the Moyie Compressor Station, which will limit Alberta/British Columbia receipt capacity to 2,118 MMcf/d. Recent nominations there have ranged from 1,906 MMcf/d to 2,259 MMcf/d, NOVA said, adding that “all efforts are being taken to maximize the receipt capability and minimize the outage duration.”