Florida Gas Transmission extended an Overage Alert Day that began Tuesday through at least Wednesday, citing forecasts of warm weather in Florida. The tolerance for negative daily imbalances was loosened to 25% Wednesday from 20% the day before.

Sea Robin Pipeline reported that the Sea Robin Processing plant operated by Amerada Hess shut down unexpectedly last Saturday. The plant continues to dehydrate during this outage, the pipeline said. However, if it is notified by any downstream pipeline that Sea Robin gas can no longer be accepted, shippers will be given as much notice as possible of the need to move their gas to other delivery points.

With testing of its Clay Basin storage facility complete, Questar said injection capacity was 330,000 Dth/d effective Wednesday.

Columbia Gulf will begin maintenance May 1 at its Regency Intrastate interconnect in Louisiana and expects the work to take about a week to complete. During this time Columbia Gulf will not accept receipt or delivery nominations at this meter.

©Copyright 2006Intelligence Press Inc. All rights reserved. The preceding news reportmay not be republished or redistributed, in whole or in part, in anyform, without prior written consent of Intelligence Press, Inc.