Compressor failure has cut Fidlar Station capacity to 90,000-100,000 Dth/d until Nov. 21 or further notice, Questar said. Shippers may reduce adverse scheduling impact by using the TransColorado delivery point, it added.

Gulf South extended scheduled maintenance at Montpelier Compressor Station in St. Helena Parish, LA through Nov. 29. The project began Sept. 3 and previously was set to end Nov. 15 (see Daily GPI, Aug. 28).

Underwater valve repairs on Transco‘s South East Louisiana Lateral, previously expected to begin Nov. 14 (see Daily GPI, Nov. 12), are now scheduled to begin either Monday or Tuesday of next week, depending on weather, and will last approximately three days, causing the shut-in of four offshore receipt meters.

©Copyright 2003 Intelligence Press Inc. All rights reserved. The preceding news report may not be republished or redistributed, in whole or in part, in any form, without prior written consent of Intelligence Press, Inc.