Rover

Ohio EPA Asks FERC to Wait as Rover Pushes For HDD Restart

Ohio EPA Asks FERC to Wait as Rover Pushes For HDD Restart

Rover Pipeline LLC continues to press FERC on a request to restart horizontal directional drilling (HDD), filing supplemental information and third-party analyses to persuade the Commission to lift a May moratorium.

September 14, 2017
Rover Presses FERC for HDD Restart; Ohio EPA Urges Patience

Rover Presses FERC for HDD Restart; Ohio EPA Urges Patience

Rover Pipeline LLC continues to press FERC on a request to restart horizontal directional drilling (HDD), filing supplemental information and third-party analyses to persuade the Commission to lift a May moratorium.

September 13, 2017
First Rover Volumes a Sign of Growth to Come in Appalachia

First Rover Volumes a Sign of Growth to Come in Appalachia

Now that Energy Transfer Partners LP’s (ETP) Rover Pipeline is officially up and running, offering more than 700 MMcf/d out of eastern Ohio, the market is getting its first taste of the project’s potential impact on Appalachian production and pricing.

September 12, 2017
Rover Pipeline Start-Up Foreshadows Growth in Appalachia

Rover Pipeline Start-Up Foreshadows Growth in Appalachia

Now that Energy Transfer Partners LP’s (ETP) Rover Pipeline is officially up and running, offering more than 700 MMcf/d out of eastern Ohio, the market is getting its first taste of the project’s potential impact on Appalachian production and pricing.

September 11, 2017
Dominion South Boosted as Rover Phase 1A Now Flowing 600 MMcf/d-Plus

Dominion South Boosted as Rover Phase 1A Now Flowing 600 MMcf/d-Plus

Energy Transfer Partners LP’s Rover Pipeline was flowing just above 600 MMcf/d out of eastern Ohio Wednesday after ramping up over the holiday weekend, helping to lift Appalachian Basin prices amid recent weakness at regional hubs.

September 6, 2017
Rover Phase 1A Flowing About 600 MMcf/d, Giving Appalachian Prices A Lift

Rover Phase 1A Flowing About 600 MMcf/d, Giving Appalachian Prices A Lift

Energy Transfer Partners LP’s Rover Pipeline was flowing just above 600 MMcf/d out of eastern Ohio Wednesday after ramping up over the holiday weekend, helping to lift Appalachian Basin prices amid recent weakness at regional hubs.

September 6, 2017

Ohio EPA Says Rover Missing Stormwater Permit, Has Complied With Other Orders

FERC on Thursday authorized Rover Pipeline LLC to place Phase 1A of its project into service, just in time to meet backer Energy Transfer Partners LP’s target for late summer start-up.

August 31, 2017

FERC Says Rover Phase 1A Good to Go, Authorizes Service

FERC on Thursday authorized Rover Pipeline LLC to place Phase 1A of its project into service, just in time to meet backer Energy Transfer Partners LP’s target for late summer start-up.

August 31, 2017

FERC Assigns Rover More Homework Before HDD Restart

FERC on Tuesday provided Rover Pipeline LLC with an updated list of measures the company would need to take before resuming horizontal directional drilling (HDD) activities for the 710-mile, 3.25 Bcf/d natural gas transmission project.

August 22, 2017

Rover Asks FERC for OK to Start Up Phase 1A by Aug. 31

Energy Transfer Partners LP’s (ETP) Rover Pipeline LLC asked FERC on Friday for authorization to begin service by Aug. 31 on Phase 1A.

August 18, 2017
1 5 6 7 8 9 13