El Paso will have the “B” Plant at Williams (AZ) Station downfor maintenance June 21-23, reduing North Mainline capacity in SanJuan Basin by 100 MMcf/d. From June 28 through July 7, individualWilliams “B” compressors will be off-line, cutting North Mainlinecapacity by 25 MMcf/d June 28-July 2 and by 40 MMcf/d July 3-7.

Due to high linepack, NOVA changed its daily imbalance toleranceMonday to 0/-20% until further notice.

NGPL will discontinue dial-up access to its DARTplus electronicbulletin board via the ReachOut software program effective July 1.From that date on, all DARTplus access must be through theInternet.

Pacific Gas & Electric had a high-inventory Stage 1 OFO ineffect Saturday and Sunday but ended it Monday.