Long-term offtakers of Venture Global LNG Inc.’s Calcasieu Pass terminal in Louisiana are again pressing FERC to make the export project developer provide information about the facility, this time targeting a request to extend the commissioning process.

Earlier this month, Venture asked the Federal Energy Regulatory Commission to extend the deadline for its 10 million metric tons/year (mmty) liquefied natural gas terminal to reach full operations by a year. The first commissioning cargo was loaded from the facility in early 2022, making it the fastest U.S. project to go from a final investment decision to first liquefaction. However, numerous issues with its equipment have been reported, mostly centered around its heat recovery steam generators for liquefaction blocks seven...