Pacific Gas & Electric kept a Stage 3 high-inventory OFO declared for Saturday in place through Sunday, cutting the imbalance tolerance from 1% to zero. No OFO was in effect Monday or today.

A new Henry Hub interconnect has been completed between affiliated pipelines Trunkline and Sea Robin. The interconnect can move 100 MMcf/d between the two systems.

El Paso will shut in Line 1105 in Crane and Ector Counties, TX for repairs July 18-25. On July and 19 the IWARWADD interconnect will not be able to deliver to El Paso, while another 24 points will be limited to a total volume of 230 MMcf/d (a reduction of about 90 MMcf/d from normal). In the July 20-25 period, IWARWADD can deliver to El Paso but will share in the 230 MMcf/d limitation along with the other points.

©Copyright 2001 Intelligence Press Inc. All rights reserved. The preceding news report may not be republished or redistributed, in whole or in part, in any form, without prior written consent of Intelligence Press, Inc.