Rockies Express (REX) said it has postponed until March previously scheduled Feb. 24-25 maintenance at its Lost Creek booster station, which will affect nominations at the Lost Creek Sweetwater location. REX will post the new dates for this outage in its March maintenance schedule.

ANR said it has not yet received its permit from Minerals Management Service for facility repairs to commence at Eugene Island (EI) 296. In addition, dewatering and commissioning of the various pipeline segments from Green Canyon to ANR’s EI 188 complex will require more time than first expected, the pipeline added. “After assessing the impact of these two issues, ANR now expects the EI 296 facilities will not be available for service until at least April 15,” ANR said.