With its linepack projected to bump up against maximum target levels in the next couple of days, Pacific Gas & Electric issued a customer-specific OFO for Thursday.

Columbia Gulf said a new mainline delivery point to Texas Eastern in Adair County, KY is expected to begin flow Oct. 9.

NGPL will inspect the two electric compressors at Station 302 in Montgomery County, TX Oct. 3-7 (one day longer than previously scheduled). Both units will be unavailable for 12 hours each day, which will lower eastbound capacity into Segment 25 (TexOk Zone), NGPL said. ITS/AOR and Secondary out-of-path transports will not be available.

Panhandle Eastern said an outage of the Montezuma Station for header piping tie-in that had been scheduled to begin Monday has been postponed until Nov. 1-3. Montezuma capacity will be limited to 1,325 MMcf/d during the outage.

©Copyright 2006Intelligence Press Inc. All rights reserved. The preceding news reportmay not be republished or redistributed, in whole or in part, in anyform, without prior written consent of Intelligence Press, Inc.