Northern Natural Gas declared a System Overrun Limitation for all market-area zones effective Thursday.

Transco said pipe reconfiguration work at the Brazos A-20 platform, delayed twice from anticipated early February starts (see Daily GPI, Feb. 3), began Wednesday and is expected to last about 10 days. In addition to the previously announced suspension of nominations at two nearby platforms during the project, the Brazos 544 location also will be affected, the pipeline said.

Replacement of Bondad Station’s 2A unit, which was to have begun Wednesday, has been postponed until Feb. 17-March 1, El Paso said. The work will reduce station capacity by about 80 MMcf/d.

NOVA will be restricting services in advance on the 36-inch Grande Prairie Mainline to allow for system integrity work starting Feb. 27. Effective Feb. 20, all Firm Service transfers within segments #1 UPRM, #2 PRLL, #3 NWML, # 4 GRDL, # 5 WAEX, # 7 GPML, #26WRSY and #27 LPRM must occur downstream only and no transfers into these areas will be permitted. See the bulletin board for a list of stations excluded from the restrictions.

©Copyright 2004 Intelligence Press Inc. All rights reserved. The preceding news report may not be republished or redistributed, in whole or in part, in any form, without prior written consent of Intelligence Press, Inc.