Scrubber

Transportation Notes

El Paso will be working on the Gallup C Station scrubber filters Dec. 1-2. From an estimated base of 2,880 MMcf/d for San Juan Basin and San Juan Mainline, capacity will be reduced by 295 MMcf/d each day, the pipeline said.

November 19, 2010

Transportation Notes

El Paso had scheduled its Alamo Lake Station to be down Jan. 31 to change inlet scrubber and fuel filters. But because the units have tripped several times recently, the project has been accelerated to occur Friday. It will reduce capacity of the Havasu Crossover by 150 MMcf/d. The work will coincide with a scheduled outage of Line 1208 on the North Mainline to mitigate overall impact.

January 24, 2002