FERC Responds to Sabal Trail Push Back, Releases Draft Supplemental EIS

FERC Responds to Sabal Trail Push Back, Releases Draft Supplemental EIS

FERC issued a draft supplemental environmental impact statement (EIS) Wednesday for the Sabal Trail Pipeline and two related pipeline expansions, addressing an Aug. 22 appeals court opinion that vacated and remanded its certificate for the projects.

September 28, 2017

Greens File for Nexus Rehearing, Again Cite Sabal Trail Ruling

A coalition of environmental groups led by the Sierra Club filed a rehearing request Thursday challenging FERC’s recent certificate approving the Nexus Gas Transmission natural gas pipeline and related projects.

September 22, 2017
Sabal Trail Gets OK to Start Up More of Phase 1, Grow Capacity to 830,000 Dth/d

Sabal Trail Gets OK to Start Up More of Phase 1, Grow Capacity to 830,000 Dth/d

FERC on Monday authorized Sabal Trail Transmission LLC to place more of the natural gas project’s Phase 1 facilities into service, increasing its total capacity to 830,000 Dth/d.

July 7, 2017

Sabal Trail Seeks FERC OK to Begin Service in Late May

Sabal Trail Transmission LLC is seeking FERC authorization to place part of its 1.07 million Dth/d pipeline into service by the end of this month.

May 19, 2017

FTC Orders Gulfstream Divestiture in Energy Transfer-Williams OK

The U.S. Federal Trade Commission (FTC) on Thursday cleared Energy Transfer Equity LP’s (ETE) proposed acquisition of The Williams Companies Inc. (WMB) and specified assets to be divested.

June 9, 2016
Shovels Ready For Florida-Focused Hillabee Expansion

Shovels Ready For Florida-Focused Hillabee Expansion

Williams Partners LP said Friday it expects to begin construction soon on its Hillabee Expansion Project, which would add capacity to the Transcontinental Gas Pipe Line (Transco) system in three phases in order to serve Florida demand via the Sabal Trail Transmission project.

March 11, 2016

FPL Cuts Rates Again, Thanks in Part to Cheap NatGas

Cheap natural gas and increased efficiencies are driving down costs for customers of Florida Power & Light Co. (FPL). State regulators have approved a rate cut to start next month along with the commissioning of FPL’s Port Everglades Next Generation Clean Energy Center.

March 2, 2016

Sabal Trail, Related Projects Get Favorable FEIS

FERC staff issued a favorable final environmental impact statement (FEIS) for the Southeast Market Pipelines (SMP) Project, which is composed of the Sabal Trail Transmission LLC project, the Hillabee Expansion and Florida Southeast Connection projects.

December 18, 2015

EPA Takes Back October Criticisms of Sabal Trail Pipeline Project

Upon consideration of revised and additional data, the U.S. Environmental Protection Agency (EPA) has taken back its criticism of the Sabal Trail Pipeline, a project of Spectra Energy Corp. and NextEra Energy Inc.

December 17, 2015

ALJ Recommends Florida Permit For Sabal Trail

The Sabal Trail pipeline project scored a regulatory victory last Friday when an administrative law judge (ALJ) recommended that Florida regulators approve a permit for the pipeline over the objection of environmentalists.