Pacific Gas & Electric did not extend a two-day high-inventory OFO beyond Thursday.

Sonat has canceled line maintenance on the Logansport Field 15 Line that was scheduled to begin Oct. 1. Maintenance is still scheduled for west of the Perryville (LA) Regulator Station beginning Oct. 1; it will cut capacity upstream of Perryville by about 120 MMcf/d. This work should be completed around Oct. 3. Additionally, Sonat will be performing maintenance on the 14-inch Logansport Line on Oct. 2, during which no receipts upstream of Logansport (LA) Compressor Station will be accepted for period of six to eight hours.

The operator of the Jackson Prairie Storage facility will conduct the annual bottom hole pressure test Sept. 30-Oct. 4, during which the facility will be shut in. However, Northwest will accept injection nominations for the Sept. 30 gas day. If operationally feasible, the bottom hole test may be started before Sept. 30. In the event of an earlier test, Northwest will post an update on its bulletin board.

ANR has scheduled upcoming pipe maintenance along its Southwest Mainline between Main Line Valves 18 and 19 located in Kansas in the Southwest Southern Fuel Segment (ML-5), followed by engine maintenance at the Havensville (KS) Compressor Station in the same segment. The work will reduce mainline capacity by 100 MMcf/d Oct. 1-4 and by 115 MMcf/d Oct. 7-18. Based on current nominations, ANR anticipates that the reductions may result in the curtailment of IT and Firm Secondary nominations.

©Copyright 2002 Intelligence Press Inc. All rights reserved. The preceding news report may not be republished or redistributed, in whole or in part, in any form, without prior written consent of Intelligence Press, Inc.