Due to a change in schedule, Tennessee was unable to deliver gas for processing to the Yscloskey Plant in southeast Louisiana beginning Wednesday. Customers were required to reduce PTR nominations for Yscloskey to zero until further notice.

NOVA will shut in the Welling Meter Station for eight hours today to allow a producer tie-in. A similar project will cause the shut-in of the Pete Lake Meter Station for 12 hours Friday.

El Paso proposes to pig the Samalayuca Lateral beginning at 7 p.m. MDT Oct. 26 and ending at 6 p.m. Oct. 28. The work would reduce lateral capacity to about 30 MMcf/d. The schedule is subject to change, El Paso said. It also reported that Lincoln Station turbine repairs have been extended through today, keeping San Juan Crossover capacity reduced by 80 MMcf/d.

ANR has scheduled installation of pig launcher/receiver facilities on the 20-inch CILCO Lateral (Line 326) in Illinois for Oct. 23-27. The Princeton-CILCO meter station will be shut in during the work, which had previously been set for Oct. 22-26 (see Daily GPI, Oct. 1).

Sonat reported receiving an inquiry from affiliate El Paso Merchant Energy concerning the Macon, GA area point. The pipeline responded that IT service from the Elba Island LNG facility, which is being reactivated, to Macon “may not be highly reliable because of the configuration of the area point.”