ANR Pipeline said it has completed maintenance on its Sandwich compressor station and has lifted capacity restrictions on its Southwest Mainline

Gulf South Pipeline Co. said it will be performing planned maintenance at the Carthage compressor station #2 on Unit #1 beginning June 14 and continuing for approximately 10 days. Capacity through the compressor station could be reduced by as much as 30,000 Dth during this maintenance.

Pacific Gas & Electric‘s California Gas Transmission has announced another high-inventory system-wide stage 2 OFO for flow day Thursday. The noncompliance charge is $1/Dth with a 10% tolerance band. The pipeline filed a similar OFO for flow day Wednesday (see Daily GPI, May 5).

Williams reported that its Northwest Pipeline will only be able to deliver 120,000 Dth/d on the Reno lateral during scheduled maintenance near Mountain Home for gas days May 5-7.

Rockies Express Pipeline said beginning Wednesday and continuing until further notice it is at capacity for quantities delivered to Tenn/Guernsey. Based on the current level of nominations, IT/AOR and secondary quantities are at risk of not being scheduled, the pipeline said.