ANR said Tuesday it has completed unplanned engine maintenance at the Sandwich (IL) Compressor Station and lifted associated capacity restrictions (see Daily GPI, Oct. 1).

In an effort to avoid future issues related to flooding and/or erosion, Northwest reported having constructed a new mainline route at the Toutle River crossing in southwest Washington state. In order to tie in the new piping, Northwest needs to shut in that section of mainline Oct. 13-14. Available mainline capacity at the Toutle River crossing will be reduced to zero on those dates. Current Primary nominations through the Toutle River crossing are approximately 90,000 Dth/d, Northwest said.

CIG said the new Oyster Ridge receipt point in Wyoming became available for service Monday. The Enterprise Gas Processing-operated point has a capacity of 150 MMcf/d.