Pacific Gas & Electric did not extend a high-inventory OFO with zero imbalance tolerance beyond Saturday.

Tropical Storm Bill is delaying the 527A-700 riser and valve replacement project as follows, Tennessee said: through July 3, physical activity remains suspended at seven meters on Line 527A-700. From July 1 through July 17, activity will be suspended at two more meters. Tennessee also said Monday the 300 Line filter separator installation project that had been scheduled for July 1-2 will be delayed until after Sept. 1 because “recent rain in the area prevents safe excavation at this time.”

The tropical storm also forced another postponement of third-party salvage work on ANR‘s system at Ship Shoal 207 associated with damage from Hurricane Lili last year (see Daily GPI, June 30). The pipeline again will await 48 hours’ notice from the contractor of the work’s commencement; it will require the shut-in of 12 meters between Eugene Island 188 and Ship Shoal 207

Northern Natural Gas reported experiencing a force majeure situation at the Beaver County (OK) Nos. 13, 12 and 3 compressor stations. They were shut in for Friday’s gas day until further notice.

©Copyright 2003 Intelligence Press Inc. All rights reserved. The preceding news report may not be republished or redistributed, in whole or in part, in any form, without prior written consent of Intelligence Press, Inc.