Construction of the Southeast Gateway and Coastal GasLink (CGL) natural gas pipeline projects is the top priority for TC Energy Corp. in 2023, management said.

southeast

CEO François Poirier hosted a conference call in late April to discuss the Calgary-based pipeline giant’s first quarter earnings.

In Mexico, the Southeast Gateway offshore pipeline remains on track to enter service in mid-2025. TC is developing the 1.3 Bcf/d pipeline in partnership with Mexico’s state power company Comisión Federal de Electricidad (CFE).

The project “is proceeding according to cost and schedule,” Poirier said. TC has “obtained key federal environmental authorizations and local permits for the project,” he added. “Critical long lead items including the offshore vessel have been secured...