It looks as though Millennium Pipeline’s long wait for a FERC ruling is going to last a little longer. Instead of getting a speedy Final Environmental Impact Statement (FEIS), the pipeline must wait until FERC can examine its proposed route change in New York, Daniel M. Adamson, director of the Office of Energy Projects, told project sponsors.
Sweat
Articles from Sweat
Millennium Has to Sweat it Out a Little Longer
It looks like Millennium Pipeline’s long wait for a FERC rulingis going to last a little longer. FERC’s Daniel M. Adamson,director of the Office of Energy Projects, turned down a request byMillennium sponsors to exclude from its Final Environmental ImpactStatement an assessment of a proposed route change in WestchesterCounty, NY. Millennium was seeking a speedy FEIS but now will haveto wait until the Commission reviews its route change.
May 11, 2000