Rover Pipeline LLC is appealing FERC’s denial last month of a blanket certificate for routine construction activities, challenging the Commission’s conclusions regarding the demolition of a historic home near a proposed compressor station.
Rover
Articles from Rover
Rover Cleared to Start Construction by FERC
FERC gave the go-ahead Friday to begin construction on the $4.2 billion Rover Pipeline and related Panhandle and Trunkline backhaul projects.
Rover Seeks OK to Clear More Trees, Has Water Quality Permits in Hand
Backers of the Rover Pipeline pressed FERC Friday to issue a notice to proceed (NTP) with tree clearing activities for all areas of the project in Pennsylvania, West Virginia and Michigan.
After FERC Marathon of Pipeline Approvals Some NatGas Projects Still Stranded
The dust has settled after a busy week at FERC, and while several major natural gas pipeline projects have certainty moving forward, others face risks of delay as the Commission heads into a quorumless stretch.
Rover Gets FERC Order Just in Time
East-to-west Appalachian natural gas mega project Rover Pipeline LLC finally has FERC’s blessing, securing approval to move forward with construction more than six months after getting its final environmental impact statement (FEIS).
Briefs — BridgeTex Pipeline
BridgeTex Pipeline Co. LLC, which is owned 50/50 by Magellan Midstream Partners LP and Plains All American Pipeline LP, is expanding its current capacity from the Permian Basin of 300,000 b/d to 400,000 b/d. Expansion capacity is expected to be available in the second quarter following enhancements to existing pumps and related equipment. The 20-inch diameter BridgeTex system transports Permian crude oil from Colorado City, TX, to the Houston Gulf Coast area. Beginning early in the second quarter, a new origin point at Bryan, TX, which is 100 miles northwest of Houston, will begin operations to accept shipments from the Eaglebine region for delivery to Houston.
FERC Timing on Rover Decision Could Have Big Impact as Deadline to Avoid Delay Nears
FERC needs to approve the Rover Pipeline Project this week in order to avoid delays, project backers told the Commission in a filing earlier this month.
‘A Tense Few Days’ For Producers, Developers as FERC Mulls Rover Decision, Analysts Say
FERC needs to approve the Rover Pipeline Project this week in order to avoid delays, project backers told the Commission in a filing earlier this month.
Rover Says It Must Start Tree Clearing Mid-January, Urges FERC Go-Ahead
Rover Pipeline LLC is urging FERC to approve its certificate application by the end of this month, warning that if it can’t start tree clearing by mid-January the project “very likely will be delayed for up to a full year.”
FERC Must OK Construction by End of Month to Avoid Delay, Rover Says
Rover Pipeline LLC is urging FERC to approve its certificate application by the end of this month, warning that if it can’t start tree clearing by mid-January the project “very likely will be delayed for up to a full year.”