Provisionally

Industry Briefs

The California Energy Commission (CEC) siting committee provisionally recommended approval of plans by a unit of NRG Energy Inc.to build a 558 MW combined-cycle gas-fired power plant on 23 acres of NRG’s existing 100-acre Encina generation plant site in Carlsbad, CA. The committee is seeking input on determining if the current repowering plans provide “extraordinary public benefit” under the criteria established by the South Carlsbad Coastal Redevelopment Project Area Plan. That enhanced benefit might come from NRG’s plans for removal of the existing 900 MW gas-fired plant. If licensed by the CEC, construction of the plant is expected to take about 25 months. NRG has said construction could begin by the end of the third quarter. Existing gas-fired Units 1, 2 and 3 at the larger site would be retired.

May 11, 2011