A roundup of news and commentary from NGI’s LNG Insight

  • Train 3 at Freeport LNG was in the process of restarting on Friday, according to a source with knowledge of the matter. An electrical motor that was damaged by severe cold in January has been repaired and is back online. Feed gas nominations were up slightly Friday. Following inspections, Freeport will now make upgrades requiring more work on Trains 1 and 2. An inspection on Train 2 is currently “progressing well,” the source said. Train 1 will be shut down for inspections and work once Train 2 is finished. 
  • FERC again excluded Venture Global LNG Inc.’s CP2 project from the agenda for next week’s meeting and will not decide on the company’s application for approval that was filed in 2021. The company, which said...