NGI The Weekly Gas Market Report
NGI Archives | NGI All News Access
Coastal OR LNG Project Delays FERC Filing; Another Plan Revived
As a competing plant up the coast at the mouth of Columbia River begins the FERC pre-filing process, proponents of the Jordan Cove liquefied natural gas (LNG) terminal project have had to delay by three months their filing to the federal regulatory agency because of additional pre-filing environmental review work on a separate-but-affiliated 230-mile large-diameter pipeline that will connect with the LNG terminal.
Earlier this month, Oregon LNG, a unit of Leucadia National Corp., confirmed it was beginning the pre-licensing review phase with the Federal Energy Regulatory Commission to build a 117-mile pipeline along the Oregon side of the Columbia River that would link the proposed LNG terminal near Warrenton, OR, with the major interstate pipelines traversing Oregon’s Interstate 5 corridor.
For backers of the Coos Bay facility, the filing postponement also will delay a timetable they released in March calling for construction to start in June 2008. The construction would now be delayed until the fourth quarter of 2008, according to Bob Braddock, the Jordan Cove LNG project manager at Coos Bay.
Earlier this spring, Braddock said his companies expected to make a formal joint filing to FERC in June to cover both Jordan Cove LNG and the Pacific Connector Pipeline. At the time, he said both had nearly completed the pre-filing phase of the environmental assessment. The backers expected to have a draft environmental impact statement and report completed within four months after filing and get a final permit to begin construction by June 2008 with much of the critical work completed in the pre-filing phase to expedite processing, Braddock said.
FERC staff have now requested that the pipeline developers provide a third set of resource reports, which caught them a bit by surprise, Braddock said, noting that filing won’t be done until later this month. “Therefore, our filing date is now targeted for Sept. 4,” Braddock said. “You have to wait 60 days after the last resource reports get filed to make the overall project filing.”
Braddock reiterated that under new FERC procedures both the Jordan Cove terminal and the linked pipeline project must be filed concurrently at the FERC.
Fort Chicago LNG II LP and engineering firm EDP LLC are the backers of the terminal, which is seeking potential sources of LNG as it moves through the permitting/siting process. Fort Chicago also has a stake in Pacific Connector Pipeline as a partner along with units of The Williams Companies and PG&E Strategic Capital Inc. The latter trio so far has picked up nonbinding interest in pipeline capacity that the companies say equals 1.5 Bcf/d.
“Clearly, there is plenty to be done, so we’ll be working on state permits and some of the construction contract agreements,” Braddock said. “So we’re just shifting the emphasis for the time being from environmental to more commercial construction issues that involve engineering and local county/water permits.”
As for the competition in Oregon in which Jordan Cove is one of five separate LNG terminal proposals and the only one on the Pacific Coast, Braddock said he understands that Oregon LNG at the very end of May made its FERC/NEPA [National Environmental Protection Act] pre-filing process. “So I think they are official now,” he said.
A set of private investors has formed Vancouver, WA-based Oregon LNG to pursue a receiving terminal at the mouth of the Columbia River on the Oregon. The fledgling company last January obtained the management and development rights for Chapter 11-bound Calpine Corp.’s Skipanon project.
The company announced earlier in June it is seeking a permit to build a 117-mile natural gas transmission pipeline from the proposed receiving terminal site easterly along the Columbia to a point in the Portland metropolitan area where it would interconnect with the existing pipeline grid near Molalla, OR.
Oregon has four other active proposals for LNG terminals — three upstream along the Columbia River in Oregon and one at Coos Bay along the southern Pacific Coast of the state. The latter project, Jordan Cove, was slated to make a filing this month to FERC.
Oregon LNG told local news media that it filed preliminary plans May 31 with FERC for building the 1 Bcf/d LNG facility and a pipeline capable of transporting up to 1.5 Bcf/d. The company proposes to follow an existing power transmission corridor through most of the six counties it would traverse from the receiving terminal. Three local hearings are to be held in communities this month along the route and in Warrenton, the proposed site for the LNG terminal for which Calpine had completed preliminary site work.
Two former Calpine executives, Peter Hansen and Mohammed Alrai, are principal officers in Oregon LNG. However, the firm’s website does not indicate who the principal backers for the company are, and officials at the Oregon Public Utility Commission and energy department had no details on the company’s ownership.
A project farther in from the coast and along the banks of the Columbia, Northern Star Natural Gas Co.’s Bradwood Landing, is the furthest along in the permitting process, and in March it received a favorable U.S. Coast Guard report, saying the lower Columbia River is suitable for LNG deliveries as long as several safety and security conditions are met.
Both Northern Star and Calpine in the past have worked hard selling the concept of LNG in the local communities. There is opposition from the Columbia River Clean Energy Coalition that has publicly said proposed LNG facilities “present the quintessential environment debate.”
©Copyright 2007Intelligence Press Inc. All rights reserved. The preceding news reportmay not be republished or redistributed, in whole or in part, in anyform, without prior written consent of Intelligence Press, Inc.
© 2024 Natural Gas Intelligence. All rights reserved.
ISSN © 2577-9877 | ISSN © 1532-1266 |