Transportation Notes

Transportation Notes

NOVA estimated that repairs to a flange assembly leak on its North Lateral (see Daily GPI, May 17), which started Wednesday, would take 24-36 hours to complete. Some receipts upstream of Dusty Lake Compressor Station are being curtailed by the work.

PG&E Gas Transmission-Northwest expected to complete work on its A-Line Wednesday night and said Kingsgate capacity would rise from 2,050 MMcf/d to 2,280 MMcf/d for today's gas day, limited by the continuing outage of Unit 5-C. With the A-Line back in service, capacity for deliveries into Northwest at Spokane, WA, will return to normal (see Daily GPI, May 17), PG&E GT-NW said.

Tennessee restored all services at 14 meters Wednesday following early completion of rehab work on the Kinder-Natchitoches Line in western Louisiana.

©Copyright 1999 Intelligence Press Inc. All rights reserved. The preceding news report may not be republished or redistributed, in whole or in part, in any form, without prior written consent of Intelligence Press, Inc.

ISSN © 2577-9877 | ISSN © 1532-1231
Comments powered by Disqus