Noting that it began performing anomaly investigations between the Pleasant View and La Plata B compressor stations Friday, Northwest said Primary firm nomination requests flowing south through Pleasant View compressor station were exceeding the available capacity of 318,000 Dth/d. Therefore, the pipeline said, a Declared Deficiency Period will be in effect for all days except Sundays through the work’s expected completion Sept. 7. Based on Pleasant View’s design capacity of 352,446 Dth/d, the Daily Deficiency Volume is 34,446 Dth/d, Northwest said. The full design capacity will be available on all Sundays.

Northwest also reminded shippers that it has several maintenance projects scheduled through the end of July. See the bulletin board for details of the projects and their capacity impacts.