Tennessee postponed for a second time the installation of a pig launcher and receiver on the 334A-100 Line north of New York City, which will cause a suspension of physical flow at the Con Ed White Plains meter. The project, which had been rescheduled for May 16-30 earlier this month (see Daily GPI, May 10), is now set for May 23-June 6, Tennessee said.

El Paso said its total shutdown of Line 1104 (Havasu Crossover) for installation of pigging facilities, originally scheduled to be finished Thursday (see Daily GPI, May 9), will continue through Friday. Full crossover capacity of 670 MMcf/d will be restored effective with Cycle 1 nominations for Saturday.

Southern California Gas extended Saturday’s high-linepack OFO through Sunday before allowing it to lapse Monday.