Texas Eastern Transmission rescheduled the outage of its Main Pass system for Monday because of Claudette. Nominations and production entering the system will be cut to zero. A third-party production platform operator is removing its platform from the system at the upstream end of the 24-inch diameter mainline. The entire system will be removed from service to accommodate the work and required piping modifications. Tetco will be unable to receive production from any meter located upstream of Venice on the Main Pass System for eight to 12 days.