Piping on the Bay Marchand 5 platform offshore southeastern Louisiana was damaged during Hurricane Lili, Tennessee said. A jackup rig is scheduled to be on site Dec. 18 to perform repairs that are expected to last eight days. Physical flow will be suspended Dec. 18-25 at the following meters: Bay Marchand 24, Grand Isle 47, South Timbalier 22, Grand Isle 48J, South Timbalier 54/55E, and South Timbalier 23. A second Bay Marchand meter will be affected, but its block number was not identified.

Noting that it received FERC authorization on May 16 to construct and operate certain modifications at its Pascagoula Compressor Station in Jackson County, MS, Destin said the facilities were placed in service Thursday, raising its certificated capacity to 1.2 Bcf/d.