Florida Gas Transmission discontinued an Overage Alert Day notice Wednesday, saying total linepack and operating conditions had improved.

Due to continuing problems with getting parts for dehydration unit maintenance at the Ivanhoe Station, Transwestern extended its outage of the Lipscomb/Mocane Lateral for a second time (see Daily GPI, July 11). The work, affecting 80,000 MMBtu/d, is now expected to run through July 26.

NGPL has scheduled line lowering work on its Crossroads Lateral for Aug. 1-2. The CROSSROADS/NGPL LAKE delivery point in Lake County, IN will be shut in during the project.

ANR said Southeast Mainline maintenance between Main Line Valves 9 and 11, previously scheduled to start yesterday and run through Saturday (see Daily GPI, July 16) has been postponed until an undetermined time.

NGPL will begin cleaning and smart pig runs Aug. 1 on the Permian #1 Line of its Amarillo System. The multiple pigging operations will move north from Station 167 to Station 112 and are expected to continue through Sept. 11. Northbound transport volumes will not be affected, NGPL said. However, scheduling cuts may be necessary for gas moving south into the Permian area that was sourced outside the Permian area. See the bulletin board for details.