El Paso Field Services has scheduled maintenance on El Pasopipeline’s Waha GE turbine for April 22-27. During that periodwellhead nominations on six gathering systems (GGOMEZHI, GTORO,GGOMEZLO, GWAHA,GSIBWAHA and GWAHARC) will be cut to zero. Someshippers on those systems may be able to flow gas to Western GasResources or Koch Pipeline, EPFS said, but must have a prior dealwith those entities for the flow days in question. EPFS must benotified of such arrangements by April 19; otherwise, “the shippersmust instruct their various producers to shut in during theduration of the maintenance.”

Starting at 12 a.m. Tuesday, Gulf South will perform about 24hours of maintenance on its West 30-inch line (Index 129) from milepole 169.23 to mile pole 182.03 just north of Houston. The workwill reduce capacity southwest of the segment by 100 MMcf/d.

The Sable Offshore Energy Processing Plant plans majormaintenance for April 16-19. Maritimes & Northeast Pipelinewill schedule no volumes for the April 17-18 gas days through theBaileyville Compressor Station,which is about three kilometerssouth of the Canadian border in Maine. Flows for April 19 will belimited to 130,000 Dth/d, about 25% of station capacity. Fullsystem capabilities are anticipated for April 20.

The Pascagoula (MS) Gas Plant has informed Destin Pipeline thata maintenance outage previously scheduled to begin April 30 willnow begin May 1 and last no longer than May 5. Both the plant andpipeline will be shut in during that period.

©Copyright 2001 Intelligence Press Inc. All rights reserved. Thepreceding news report may not be republished or redistributed, inwhole or in part, in any form, without prior written consent ofIntelligence Press, Inc.