The Line 523F-100 line-lowering project is being extended by one week through March 18 due to severe weather resulting in delays, Tennessee said. The work, previously projected for completion by Friday (March 11), is causing suspension of physical flow at the Thomas Cenac 1 (CI) and Lapeyrouse Plant Dehydration meters.

In a progress update on the new Bridgeline-Johnsons Bayou interconnect on its Louisiana Line just downstream of Compressor Station 342 in Cameron Parish, LA, NGPL said Tuesday it anticipates putting the delivery point into service Thursday of this week.