Demand exceeding capacity has resulted in a linepack loss downstream of Stations 245 and 321, Tennessee said, prompting it to issue Critical Day 1 OFOs for all LMS-PA Balancing Parities in Zones 5 and 6 effective Sunday. The OFOs will be in addition to Action Alerts implemented Friday in those zones along with one in Zone 4, Tennessee said.

The suspension of liquid deliveries on McMahon Gas Plant’s Raw Gas Transmission system posted Tuesday has been removed, Westcoast said, and all liquid receipt points on the system were allowed to resume deliveries Thursday morning.

NGPL has rescheduled completion of a 39-mile portion of the #1 line located just west of Compressor Station 802 in the Texok Zone for Feb. 8-10; it previously was set for Feb. 1-3. See the bulletin board for impact details.