Gulf South plans to begin repairs at the start of Thursday’s gas day on Index 817 (its 42-inch diameter East Texas Expansion) in DeSoto Parish, LA. In order to reduce pipeline pressures to allow the maintenance, Gulf South said it will reduce scheduled capacity to 1.165 Bcf/d in the Expansion Area 16 Receipt scheduling group, which it expects to continue through Friday.

CenterPoint told shippers it will begin maintenance April 13, expected to last for 10 days, on Line CP (its segment from the Carthage Hub in East Texas to the Perryville Hub in northeast Louisiana). The work will cause a reduction of Line CP capacity to 1.56 Bcf/d.