In an update on the impact from a recent brush fire that burned through its Aliso Canyon storage field (see Daily GPI, Oct. 16), Southern California Gas (SoCalGas) said that although the fire did not cause damage to Aliso Canyon’s major facilities, it did damage power and communication infrastructure. SoCalGas said it was working to complete the necessary repairs but did not know when the field would be back in service.

Gulf South began what it estimated as 10 days of scheduled pigging Thursday on its Index 157 and Index 140 (Halter Island to Kent Bayou) segments. A dozen receipt points are shut in during the work.

Questar said it completed the rerouting of its ML 80 segment ahead of schedule and restored ML 80 capacity to the normal 290,000 Dth/d Thursday. As a result of intermittent electrical problems with Unit #3 at Oak Spring Station earlier in the week, Questar had again delayed the ML 80 work to Tuesday through Thursday after postponing it late last week to Sunday through Tuesday (see Daily GPI, Oct. 10).

Westcoast reported that all processing trains at Pine River Gas Plant were up and running again Thursday after a total power outage Tuesday (see Daily GPI, Oct. 16). Although linepack was still low Thursday in Westcoast’s Mainline North and Mainline Central segments, the pipeline expected linepack to rise from the restored operations at Pine River.

Due to side valves being installed on the 26-inch and 30-inch diameter lines near its Eunice (LA) Compressor Station, on Monday TGT will begin bypassing volumes subject to processing at the Eunice Crosstex processing plant. Oct. 29 is the tentative date for the construction work to be completed, TGT said. Plant Thermal Reduction percentages will be zero until then, it added. TGT said it will waive the hydrocarbon dew point quality specifications in its tariff for 20 meters during this work, but reserves the right to revoke the waiver at any time for any reason. In addition, until the valve installations are finished, TGT will be unable to schedule either receipts or deliveries at the ANR-Eunice interconnect.

El Paso‘s Keystone Station in Winkler County, TX, will be down for Department of Transportation inspections and other annual maintenance Monday through Saturday next week. Capacity through the station is normally about 785 MMcf/d. No gas will flow through Keystone Monday through Thursday due to pipe replacement on Line 3026 Monday and Tuesday and on Line 1103 Wednesday and Thursday. On Friday and Saturday Keystone will be able to flow about 150 MMcf/d. The Unocal Storage Facility and Ector Power Plant upstream of Keystone will both remain on-line, providing a possible destination for Keystone Pool gas, El Paso said. See the bulletin board for other details and a list of points where receipts could be reduced by the Keystone work.

Transwestern postponed until 2009 an outage of the La Plata Compressor Station due to pipe cleaning work in its Ignacio to Bloomfield section that had previously been scheduled for Oct. 21-24.

Citing scheduling conflicts, Southern Natural Gas postponed until Nov. 4-5 pigging operations on the 14-inch diameter Logansport Line and the 16-inch diameter Logansport Supply Line in North Louisiana west of Bienville Compressor Station. The work previously had been set for Tuesday and Wednesday of next week.

TransCanada is holding an open season through 10 a.m. MDT Wednesday for both Annual Firm Service and Short Term Firm Service on its Foothills BC (Zone 8) operation. Following this open season, any remaining capacity will be posted into daily open seasons. Call Bruce Newberry at (403) 920-5579 or Dan Morrison at -6139 for more information.