Westcoast reported completing repairs to the #10 sulfur train at its Fort Nelson Gas Plant and lifted the associated 5% Firm H2S (hydrogen sulfide) Overproduction Charge constraint at the start of Thursday’s gas day.

NGPL said a gas quality problem at the CEM/NGPL BECKHAM receipt point in Beckham County, OK, has been resolved and the point became available for nominations effective for Thursday’s gas day.

El Paso will take San Juan Crossover capacity to zero June 16-17 for installation of a new mainline valve on Line 1300. Other maintenance will reduce the crossover’s capacity (from a base of 628 MMcf/d) by 110 MMcf/d on June 18 and by 300 MMcf/d June 23-26.

Rockies Express (REX) said late Wednesday afternoon a gas quality problem exists at the Lost Creek Wamsutter receipt point in Sweetwater County, WY. “A reduction in scheduled quantities may be necessary as REX continues to monitor the situation and assess the impact to its facilities,” the pipeline added.

©Copyright 2008Intelligence Press Inc. All rights reserved. The preceding news reportmay not be republished or redistributed, in whole or in part, in anyform, without prior written consent of Intelligence Press, Inc.