Tennessee said the completion date for installation of a pig launcher and receiver on the 334A-100 Line north of New York City has been delayed until July 3. The work, which requires the suspension of physical flow at the Con Ed White Plains meter and has seen several previous delays, most recently had been expected to wind up Tuesday, the pipeline said.

Tennessee also said a filter change at Compressor Station 409 in Edinburg, TX that had been scheduled for Thursday was postponed until further notice. Due to loss of horsepower during this work, customers south of the station could experience lower than normal operating pressures and deliveries to the Pemex and Rio Bravo meters could be limited, Tennessee said.