Florida Gas Transmission said a Zone 1 constraint resulting fromhydrostatic testing immediately downstream of Station 4 in MatagordaCounty, TX will be completed by Thursday and it is accepting all Zone1 nominations for that gas day. The maintenance period, which beganOct. 20, 2000 and was originally scheduled to end Dec. 1, 2000, wasextended several times (see Daily GPI, Jan.24).

Northern Natural Gas said 15,000 MMBtu/d is affected at theGPM/NNG Farnsworth receipt point Tuesday and today as it repairs anA-line leak.

©Copyright 2001 Intelligence Press Inc. All rights reserved. Thepreceding news report may not be republished or redistributed, inwhole or in part, in any form, without prior written consent ofIntelligence Press, Inc.