Sendout capacity at the Trunkline LNG facility near Lake Charles, LA is limited to 700 MMcf/d until further notice due to two vaporizers being taken out of service for unscheduled repairs, the company said Friday.

With maintenance that required the shutdown of Questar‘s Clay Basin storage facility due to be completed Saturday, injection capacity would be 300,000 Dth/d effective May 1, the pipeline said.

Gulf South reported Friday the completion of unscheduled maintenance on Unit #2 at the Marksville Compressor Station in Louisiana (see Daily GPI, April 29).

©Copyright 2005Intelligence Press Inc. All rights reserved. The preceding news reportmay not be republished or redistributed, in whole or in part, in anyform, without prior written consent of Intelligence Press, Inc.