Florida Gas Transmission let last week’s Overage Alert Day notices lapse Saturday, then implemented new ones Sunday and Monday. Monday’s tolerance for negative daily imbalances was 15%.

A Type 6 OFO for short imbalances that Sonat issued for Monday will be canceled at the start of Tuesday’s gas day.

Northern Natural Gas issued a System Overrun Limitation day notice for Tuesday due to below-zero minimum temperatures in its Zone E/F area.

Texas Eastern reported receiving notice Saturday evening that Line 40-B, known as its Main Pass System, had sustained damage due to the placement of a jackup drilling rig. As a result, receipts along the line have been restricted to zero until further notice. No nominations were restricted for Sunday’s gas day, Texas Eastern said, but restrictions were in pace for all Main Pass nominations Monday. Imbalances caused by this temporary shutdown will need to be resolved, it added. No physical increases were being accepted from 25 meters listed on the bulletin board.

Effective Tuesday, Dominion will have no interruptible or secondary capacity available at delivery points to the Corning Natural Gas, New York State Electric and Gas, Rochester Gas & Electric, Niagara Mohawk, Fillmore Gas and National Fuel Gas Distribution systems. The action is being taken due to anticipated weather forecasts and the duration of these forecasts, as well as the anticipated corresponding firm load requirements, Dominion said. It also asked all customers located downstream of its Stateline facility and Boom Station and along the PL-1 system to monitor their hourly deliveries from Dominion and take necessary steps to minimize hourly variances in takes. And also effective Tuesday until further notice, there will be no capacity on the PL-1 system for either interruptible or secondary transportation. All primary PL-1 customers will be required to deliver to their primary points of delivery during this restriction, Dominion said.

Citing a force majeure situation at the Chesapeake LNG plant, Columbia Gas said that while the plant is currently operational, service to shippers under Rate Schedules X-131, X-132 and X-133 may be affected until the force majeure is remedied.