Scheduled northbound volumes through the Kemmerer (WY) Compressor Station continue to exceed 500,000 Dth/d, Northwest said, while its Jackson Prairie storage account continues to decrease. Shippers were told that the pipeline will evaluate conditions on a daily basis, and if it finds that not maximizing a receipt or delivery point will alleviate the Kemmerer constraint, “please be advised that Northwest will NOT maximize these points in the Timely cycle.” The pipeline was not allowing any balancing Thursday except onto its system in the segment north of Kemmerer.

NGPL resumed scheduling deliveries Thursday to the Midwestern-Kankakee meter in Kankakee County, IL (see Daily GPI, April 17), but said if Midwestern’s operational issues recur, it will notify shippers immediately.

©Copyright 2003 Intelligence Press Inc. All rights reserved. The preceding news report may not be republished or redistributed, in whole or in part, in any form, without prior written consent of Intelligence Press, Inc.