The Maritimes & Northeast Pipeline (M&N) said Tuesday that cold weather forecasts and high demand on the M&N system have triggered a number of restrictions that will be in effect until further notice. Shippers are required to schedule receipts commensurate with expected deliveries; meter operators are required to flow at scheduled volumes, and imbalance gas will not be allowed to be taken off of M&N’s system. More specifically, the pipeline said due shipper payback and/or due pipe creation imbalances will not be allowed. “If necessary, M&N may take action as permitted by the general terms and conditions of the M&N FERC Gas Tariff, including the issuance of OFOs, to minimize due pipe creation and/or due shipper payback imbalances,” M&N said.

©Copyright 2008Intelligence Press Inc. All rights reserved. The preceding news reportmay not be republished or redistributed, in whole or in part, in anyform, without prior written consent of Intelligence Press, Inc.