PennEast Pipeline Canceled After Years of Regulatory, Legal Delays

PennEast Pipeline Canceled After Years of Regulatory, Legal Delays

Seven years after it was announced, the PennEast Pipeline has been canceled following repeated regulatory and legal setbacks that have increasingly complicated other natural gas infrastructure projects across the country.  PennEast scrapped the project on Monday following what it said was “extensive evaluation and discussion” among its five member companies. The project battled landowners, environmental…

September 27, 2021
Supreme Court Rules Eminent Domain in Play as PennEast Pursues Major Natural Gas Pipeline Project

Supreme Court Rules Eminent Domain in Play as PennEast Pursues Major Natural Gas Pipeline Project

The U.S. Supreme Court has cleared a key roadblock from PennEast Pipeline Co.’s path toward finishing construction of a major natural gas pipeline in Pennsylvania and New Jersey. The high court on Tuesday ruled that the PennEast joint venture may use federal eminent domain power to condemn and acquire 42 parcels in New Jersey to…

June 30, 2021
In ‘Monumental’ Decision, Supreme Court Rules PennEast May Invoke Eminent Domain for 1 Bcf/d Natural Gas Project

In ‘Monumental’ Decision, Supreme Court Rules PennEast May Invoke Eminent Domain for 1 Bcf/d Natural Gas Project

The U.S. Supreme Court has cleared a key roadblock from PennEast Pipeline Co.’s path toward finishing construction of a major natural gas pipeline in Pennsylvania and New Jersey. The high court on Tuesday ruled that the PennEast joint venture may use federal eminent domain power to condemn and acquire 42 parcels in New Jersey to…

June 29, 2021
U.S. Supreme Court Agrees to Hear PennEast Case Versus New Jersey in Big Win for Natural Gas Project

U.S. Supreme Court Agrees to Hear PennEast Case Versus New Jersey in Big Win for Natural Gas Project

The U.S. Supreme Court has agreed to hear PennEast Pipeline Co. LLC’s case against New Jersey, which has stopped the natural gas project from condemning state-owned land.  The high court on Wednesday granted PennEast’s petition in a win for the project, which has been under development for more than five years. The pipeline is one…

February 3, 2021
Solicitor General Supports PennEast Petition for Supreme Court Review

Solicitor General Supports PennEast Petition for Supreme Court Review

The Solicitor General has filed an amicus brief supporting the PennEast Pipeline’s petition for the U.S. Supreme Court to hear its case against New Jersey’s efforts to stop the project from condemning state-owned land.  Acting Solicitor General Jeffrey B. Wall said the certificate of public convenience and necessity issued to PennEast by FERC “expressly” allows…

December 11, 2020
FERC Says PennEast May Condemn State-Owned Properties

FERC Says PennEast May Condemn State-Owned Properties

The beleaguered PennEast Pipeline got a lift on Thursday from FERC, which granted a petition for declaratory order by finding the project may condemn state-owned land as a certificate holder with the power of eminent domain.

January 30, 2020
FERC Says PennEast May Condemn State-Owned Properties

FERC Says PennEast May Condemn State-Owned Properties

The beleaguered PennEast Pipeline got a lift on Thursday from FERC, which granted a petition for declaratory order by finding the project may condemn state-owned land as a certificate holder with the power of eminent domain.

January 30, 2020
FERC Delays Action on PennEast Pipeline’s Eminent Domain Petition

FERC Delays Action on PennEast Pipeline’s Eminent Domain Petition

A request from PennEast Pipeline Co. LLC for an order interpreting the Natural Gas Act’s (NGA) eminent domain authority, which had been on the agenda for FERC’s open meeting in Washington, DC, Thursday, was postponed by the Commission until later this month.

January 23, 2020
FERC Delays Action on PennEast Pipeline’s Eminent Domain Petition

FERC Delays Action on PennEast Pipeline’s Eminent Domain Petition

A request from PennEast Pipeline Co. LLC for an order interpreting the Natural Gas Act’s (NGA) eminent domain authority, which had been on the agenda for FERC’s open meeting in Washington, DC, Thursday, was postponed by the Commission until later this month.

January 23, 2020
PennEast Seeks Two-Year Extension to Finish Project

PennEast Seeks Two-Year Extension to Finish Project

Project sponsors have asked FERC for another two years to finish constructing the PennEast Pipeline, which has struggled to obtain regulatory approvals and permits.

January 3, 2020