Delay

Magnolia LNG, Pipeline Developer Seek Five-Year Extension to Build Facilities

Magnolia LNG, Pipeline Developer Seek Five-Year Extension to Build Facilities

The developer of a Gulf Coast liquefied natural gas (LNG) project that would be part of the so-called second wave buildout is seeking more time from FERC to build the export facility, citing difficulty in securing long-term offtake agreements with international customers. New York City-based Glenfarne Group LLC told the Federal Energy Regulatory Commission on…

September 14, 2020
Tellurian Delays Driftwood FID, May Drop Permian Pipeline Plan

Tellurian Delays Driftwood FID, May Drop Permian Pipeline Plan

Liquefied natural gas (LNG) developer Tellurian Inc. has delayed a final investment decision (FID) on its proposed Driftwood LNG export terminal by one year to 2021 and may drop plans to build a $4.2 billion pipeline to bring Permian Basin supply to the first phase of the project, the company’s chief said Tuesday.

June 17, 2020
NextDecade Delays Rio Grande LNG FID to 2021, Cuts Costs to Reach Finish Line

NextDecade Delays Rio Grande LNG FID to 2021, Cuts Costs to Reach Finish Line

NextDecade Corp. said Monday it now expects to make a final investment decision (FID) on its Rio Grande liquefied natural gas (LNG) export project on the South Texas coast next year as the Covid-19 pandemic continues to upend energy markets.

May 18, 2020
Sempra’s Port Arthur FID May Slip Amid Challenging Macro Environment

Sempra’s Port Arthur FID May Slip Amid Challenging Macro Environment

The current economic environment, plagued by the oil price war between Saudi Arabia and Russia and the Covid-19 pandemic, may impact the schedule for sanctioning Sempra Energy’s second U.S. liquefied natural gas (LNG) export project east of Houston.

March 27, 2020

Cameron LNG Seeks Extension for Expansion After Engie’s Exit

A Sempra Energy affiliate has asked FERC for a six-year extension to finish an expansion at the Cameron liquefied natural gas (LNG) export facility in Louisiana, citing a shakeup among its joint venture (JV) partners that has pushed back the project’s timeline.

January 29, 2020

Cameron LNG Seeks Extension for Expansion After Engie’s Exit

A Sempra Energy affiliate has asked FERC for a six-year extension to finish an expansion at the Cameron liquefied natural gas (LNG) export facility in Louisiana, citing a shakeup among its joint venture (JV) partners that has pushed back the project’s timeline.

January 29, 2020

FERC Delays EIS for Jordan Cove, OKs Feed Gas at Elba Island

FERC said the 35-day partial shutdown of the federal government has forced it to delay by more than 40 days completion of an environmental impact statement (EIS) for the Jordan Cove liquefied natural gas (LNG) export facility and the companion Pacific Connector Pipeline project in Oregon.

March 6, 2019
Two Mexico Natural Gas Pipes Delayed Further Amid Local Impasse, Says TransCanada

Two Mexico Natural Gas Pipes Delayed Further Amid Local Impasse, Says TransCanada

TransCanada Corp. has pushed back the targeted completion dates of its already delayed Tuxpan-Tula and Tula-Villa de Reyes natural gas pipeline projects because of an impasse with local authorities along the routes.

November 21, 2018
ACP Full-Service Pushed Back to 2020 Amid Setbacks; Dominion Divesting Blue Racer

ACP Full-Service Pushed Back to 2020 Amid Setbacks; Dominion Divesting Blue Racer

Parts of the Appalachia-to-Southeast Atlantic Coast Pipeline (ACP) won’t start up until mid-2020, and the project will cost more than previously thought, backer Dominion Energy announced Thursday.

November 1, 2018

EQT Says MVP Delayed to Early 2019 as Sponsors Address Legal Challenges

EQT Corp. said on Thursday the start of service on the Mountain Valley Pipeline (MVP) would be delayed by three months, as the project’s sponsors work through a pending legal challenge from the Sierra Club and other opponents.

July 26, 2018
‹ Previous 1 2 3 14