Eagle Ford Gathering LLC, a joint venture (JV) of Kinder Morgan Energy Partners LP and Copano Energy LLC, has executed two long-term agreements to provide transportation, processing and fractionation services to two operators in the Eagle Ford Shale, expanding its already significant contracted production in the South Texas play.
Crossover
Articles from Crossover
Streamlined Marcellus Bills Advance in West Virginia Legislature
Bills that would change West Virginia’s regulation of Marcellus Shale drilling — stripped of forced pooling language and proposing smaller increases to horizontal permitting fees than previously considered — were passed Thursday by House and Senate committees in the state’s legislature in Charleston.
Transportation Notes
Saying maintenance on Belen (NM) Station’s #1 turbine had been completed ahead of schedule, El Paso increased capacity of the San Juan Crossover to 650 MMcf/d Friday.
Transportation Notes
Saying Questar Crossover 16 receipt point gas quality was tested and adheres to its tariff standards (see Daily GPI, May 7), Northwest resumed accepting nominations there in Wednesday’s intraday cycle.
Transportation Notes
Previously reported maintenance on the El Paso Natural Gas will reduce capacity on the San Juan Crossover by 150 MMcf/d Sept. 18. Maintenance on the San Juan system also will cut capacity by 250 MMcf/d on Sept. 26 and by 220 MMcf/d Sept. 30-Oct.1. Window Rock 2B repairs have been completed earlier than expected. The capacity of the North Mainline was increased by 25 MMcf/d to 2,305 MMcf/d effective for Cycle 3 on Sept. 17. For operational or capacity impact questions, call Charlie Mathis at (719) 667-7712.
Transportation Notes
El Paso extended Lincoln Station compressor maintenance and water leak repairs on Belen Station’s Unit #1. San Juan Crossover capacity will continue to be reduced by 100 MMcf/d through Monday. The pipeline also said internal inspection pigging scheduled Friday (July 19) on Line 1208 will require a larger flow cut than previously announced. North Mainline capacity will be reduced by 160 MMcf/d.
Transportation Notes
El Paso extended Lincoln Station compressor maintenance and water leak repairs on Belen Station’s Unit #1. San Juan Crossover capacity will continue to be reduced by 100 MMcf/d through Monday. The pipeline also said internal inspection pigging scheduled Friday (July 19) on Line 1208 will require a larger flow cut than previously announced. North Mainline capacity will be reduced by 160 MMcf/d.
Transportation Notes
The #1 compressor at Roswell (NM) Station became unavailableFriday due to a bearing failure, causing a 30 MMcf/d reduction inSan Juan Crossover capacity, El Paso said. Repairs were expected tohave been completed Saturday.
Transportation Note
El Paso will take the Dutch Flat #1 turbine down for maintenanceDec. 20-22, reducing Havasu Crossover capacity by 40 MMcf/d.
Transportation Notes
El Paso will shut down its Blanco (NM) Plant Monday forscheduled maintenance. Several other facilities on the San JuanCrossover and North Mainline also will have maintenance. Because atotal Blanco outage will last only half a day, the net reduction ofSan Juan Basin supply Monday will be 715 MMcf/d. Downtime of the Cand D units May 18-19 and of the D unit May 20-26 will causereductions of 500 MMcf/d and 270 MMcf/d respectively.