Commissioning

Venture Global Asks FERC for 1-Year Extension of Calcasieu Pass LNG Commissioning

Venture Global Asks FERC for 1-Year Extension of Calcasieu Pass LNG Commissioning

Work at Venture Global LNG Inc.’s Calcasieu Pass export facility could stretch on until the end of the year, requiring the firm to seek an authorization extension from FERC, the company disclosed in a recent filing. The Virginia-based company has asked the Federal Energy Regulatory Commission to grant it an extra year to complete the…

February 16, 2024
Venture Global Ready to Load First Commissioning Cargo at Calcasieu Pass Terminal

Venture Global Ready to Load First Commissioning Cargo at Calcasieu Pass Terminal

Venture Global LNG Inc. on Thursday requested FERC authorization to load the first liquefied natural gas (LNG) export cargo from its Calcasieu Pass terminal in Louisiana as early as February 9. The company filed its request a day after revealing in a status report submitted to the Federal Energy Regulatory Commission that it produced first…

February 4, 2022

Cove Point Asks DOE For Commissioning LNG Cargo Authorization

Dominion Cove Point (DCP) has asked the U.S. Department of Energy (DOE) for authorization to begin exporting commissioning cargos from its liquefied natural gas (LNG) export facilities on the Chesapeake Bay in Lusby, MD.

April 13, 2017

Traders See Little Upward Follow-Through, Yet April Called 4 Cents Higher

April natural gas is set to open 4 cents higher Tuesday morning at $1.86. as traders see a market recovering from oversold conditions and fundamentals providing little reason for prices to continue higher. Overnight oil markets fell.

March 15, 2016

Brief — Sabine Pass

Cheniere Energy Inc. Thursday was granted FERC authorization to begin introducing fuel gas into the Sabine Pass liquefied natural gas (LNG) export terminal’s second train [CP11-72]. In a note published Friday, Genscape said it expected to see commissioning activities starting for Train 2 in the coming days. Commissioning “…will occur over the next several months as they perform their requirements before they introduce refrigerants and begin liquefaction,” Genscape said. Following technical delays, Sabine Pass recently sent out its first cargo, bound for Brazil, making it the first terminal to export U.S.-sourced LNG from the Lower 48 states (see Daily GPI,Feb. 24).

March 4, 2016

Briefs — Sabine Pass, Avista Utilities, Shell Chemical

Cheniere Energy Inc.’s Sabine Pass liquefied natural gas (LNG) export terminal in Louisiana is creeping closer to sending out its first cargo, according to Genscape Inc., which has been monitoring commissioning and gas delivery activity at the project. “Since commissioning began last Oct. 1 2015, Sabine has received a total of 4.55 Bcf in commissioning gas from the Creole Trail and NGPL pipelines,” Genscape said in note Tuesday. “It has also boiled off 1.92 Bcf from its regasification side that was cycled back as some of this commissioning gas. All of this gas delivered to the facility has been either flared or used to run the compressors in commissioning.” More recently, a receipt location on Creole Trail, “Sabine Pass LNG,” which was representative of the boil off gas has flipped and is now delivering small feed gas volumes (about 8 MMcf/d) to Sabine, according to Genscape, which also said in its note that first liquefaction is likely to “soon take place.” The terminal was to have sent out its first cargo earlier this year, but that was delayed by technical difficulties at the facility (see Daily GPI,Jan. 14).

February 16, 2016

Transportation Notes

CIG said it had completed repairs to the Totem Storage Field dehydration facility and would complete commissioning operations there Sunday (March 7). The associated force majeure will be terminated Monday, CIG said, and a restoration of full withdrawal operations will be implemented then.

March 8, 2010

Transportation Notes

CIG said it had completed repairs to the Totem Storage Field dehydration facility and would complete commissioning operations there Sunday (March 7). The associated force majeure will be terminated Monday, CIG said, and a restoration of full withdrawal operations will be implemented then.

March 8, 2010

Regency’s Capacity From Haynesville Poised to Double

Construction of Regency Energy Partners LP’s Haynesville Expansion Project is complete and the 121-mile line is undergoing testing and commissioning, Regency said last week. The project will transport gas from the Haynesville Shale, one of the fastest growing U.S. gas fields.

January 18, 2010

Regency Intrastate Capacity From Haynesville Poised to Double

Construction of Regency Energy Partners LP’s Haynesville Expansion Project is complete and the 121-mile line is undergoing testing and commissioning, Regency said Tuesday. The project will transport gas from the Haynesville Shale, one of the fastest growing U.S. gas fields.

January 13, 2010
‹ Previous 1 2