Rover Phase 1B Ready By 4Q, Phase 2 Tracking For Late 1Q2018, ETP Says

Rover Phase 1B Ready By 4Q, Phase 2 Tracking For Late 1Q2018, ETP Says

Rover Pipeline LLC is wasting no time restarting horizontal directional drilling (HDD) at key sites now that it has the go-ahead from FERC, but the pipeline’s full in-service date could slip to late 1Q2018, Energy Transfer Partners LP (ETP) said Tuesday.

September 19, 2017
Rover On Pace For Partial Phase 1 Service This Month, Energy Transfer Confirms

Rover On Pace For Partial Phase 1 Service This Month, Energy Transfer Confirms

The highly anticipated Rover Pipeline, a massive 3.25 Bcf/d Appalachian takeaway project scheduled to come online later this year, is on track to begin partial service this month, backer Energy Transfer Partners LP (ETP) has confirmed.

July 10, 2017

Energy Transfer Now Projects Partial Delay of Rover Phase 1

While part of Energy Transfer Partners LP’s Rover Pipeline Phase 1 remains on track for an early July start-up, the rest of Phase 1 is likely to get pushed back, a company spokeswoman said Thursday.

May 26, 2017
Rover Seeks OK to Finish HDDs For OH, WV Laterals, Tells FERC Work Already Underway

Rover Seeks OK to Finish HDDs For OH, WV Laterals, Tells FERC Work Already Underway

In a letter Tuesday responding to FERC’s May 10 order that suspended new horizontal directional drilling (HDD) for the Rover Pipeline, backer Energy Transfer Partners LP asked Commission staff to allow completion of two HDDs critical to laterals in Ohio and West Virginia.

May 17, 2017