The Federal Energy Regulatory Commission on Thursday vacated a certificate that gave ANR Pipeline the green light to build a lateral extension to provide natural gas to a planned power generation plant in Wisconsin.

ANR in February asked FERC to take this action after Badger Generating Co., which would have been served by the lateral, nixed plans to construct a proposed generation facility [CP01-79].

The $19.5 million project had called for ANR to build 13 miles of 20-inch diameter looping along the pipeline’s Racine Lateral and a 10-mile extension of the lateral to the proposed Badger plant. It would have had a deliverability capacity of 210 MMcf/d.

©Copyright 2003 Intelligence Press Inc. All rights reserved. The preceding news report may not be republished or redistributed, in whole or in part, in any form, without prior written consent of Intelligence Press, Inc.