El Paso will be working on the Gallup C Station scrubber filters Dec. 1-2. From an estimated base of 2,880 MMcf/d for San Juan Basin and San Juan Mainline, capacity will be reduced by 295 MMcf/d each day, the pipeline said.

Finishing electrical upgrades will require Kanda Compressor Station to be unavailable Dec. 7-9, Questar said. To facilitate the work, nominations to and from CIG (MAPs 171 and 871) will be netted to zero for those gas days. Currently there is 1,833 Dth/d being nominated at MAP 171 and 17,000 Dth/d at MAP 871, Questar said.

©Copyright 2010Intelligence Press Inc. All rights reserved. The preceding news reportmay not be republished or redistributed, in whole or in part, in anyform, without prior written consent of Intelligence Press, Inc.