NGPL said pipeline replacement work on segment one in its Midcontinent Zone will further reduce pressure on its system, cutting capacity from an already reduced state. The pipeline expects a complete outage on that section of the system Nov. 16-17, affecting about 15 receipt/delivery points.

PG&E extended a Stage 3 high inventory operational flow order with a 12% tolerance through Saturday. Penalties for noncompliance are $5/Dth.

ANR Pipeline said it is working on several engines at its St. John and Bridgman Compressor Stations along the Michigan Leg South in the Northern Fuel Segment (ML-7), which will reduce the total St. John W-E capacity by 150 MMcf/d (leaving 1,155 MMcf/d available) Nov 8-Nov 12. Based on nominations, the reductions will result in the curtailment of firm secondary and IT nominations.